Contact us on
Value: Under $2,000,000.00
Our Role: Head Contractor - Design & Construct
Description:
We were engaged by the Client to replace their existing Plant Room and Chillers. The Existing Chiller Plant Room was demolished and a new larger Plant Room was built on the existing roof to accommodate the New Chilled Water Plant. The site and the Data Centre operate 24 hours a day, 7 Days per week - the new works were not to interfere with the continual operation of the site and Data Centre.
This required some carefully planned design and project management to ensure business continuity of the operations. Our temporary cooling plant was used to support the Data Centre for duration of the project.